Stock management and scheduled supplies

Magnetic product lead times can range approximately from 55 days to 16 weeks, depending on the material, the required processing and the selected transport method: air freight or sea freight.
Inadequate planning can therefore lead to delivery delays, logistical difficulties and, in the most critical cases, production slowdowns or stoppages.

To reduce these risks, ODB offers stock management and scheduled supply solutions tailored to the customer's actual requirements, forecast consumption and the criticality of the component.
Depending on the specific needs, different management methods can be considered, including Dedicated Stock, Safety Stock and Buffer Stock.

Greater supply continuity, lower production risks

Dedicated Stock

Dedicated Stock means that ODB manages a quantity of material in its warehouse specifically allocated to a particular customer.

One of the most commonly used methods is a scheduled order: ODB procures the total agreed quantity, stores it in its warehouse and makes it available for subsequent deliveries according to the customer's production requirements.

The agreement can define in advance:

  • the total quantity ordered;
  • the planned quantity for each delivery;
  • the indicative call-off frequency;
  • the agreed coverage period;
  • the date by which the customer undertakes to collect the entire quantity ordered.

This means that the material is already available at ODB and can be delivered according to a shared schedule, reducing dependence on normal replenishment lead times.

Safety Stock

For particularly critical components or items with long procurement lead times, an agreed Safety Stock level can be established, i.e. a safety stock intended to reduce the risk of material shortages.

The safety level is assessed by considering factors such as:

  • the customer's average consumption;
  • demand variability;
  • procurement lead time;
  • component criticality within the production process;
  • possible fluctuations or delays along the supply chain.

Keeping a safety stock provides greater protection against unexpected changes in consumption or procurement timing.

Buffer Stock

Buffer Stock is an additional quantity of material that can be planned to temporarily absorb demand peaks, deviations from the forecast or unexpected production requirements.

It can be especially useful for supplies with variable consumption, seasonality or projects where volumes may change during the year.

The Buffer Stock quantity is agreed with the customer according to the characteristics of the supply and can be periodically reviewed based on actual consumption trends.

Magnet stock management and warehouse supply

Planning built around actual requirements

Stock management methods are always assessed case by case.
For customers with established supplies, the plan can be developed from purchasing history, normal consumption and forecasts for the following months.
For a new project or a new supply, quantities, delivery frequency and stock levels are instead defined according to forecasts, expected volumes and production schedules.

Depending on requirements, Dedicated Stock, Safety Stock and Buffer Stock can be used individually or combined within the same supply plan. 

Benefits for the customer

Where applicable, scheduled supply management can help to:

  • increase continuity and security of supply;
  • reduce exposure to long replenishment lead times;
  • make the required material available more quickly;
  • create dedicated stock for the most critical components;
  • manage possible consumption changes more safely;
  • simplify purchasing and production planning;
  • reduce the risk of delays, urgent requests and production stoppages;
  • split deliveries according to actual requirements.

Each agreement is defined transparently, establishing quantities, stock levels, delivery methods and timing from the outset.

Let's identify the most suitable solution together

Not all products, consumption patterns and supplies can be managed in the same way.
Our team is available to analyse forecasts, consumption, lead times and application criticality in order to identify the most appropriate combination of scheduled supply, Dedicated Stock, Safety Stock and Buffer Stock.
The goal is to create a supply management system aligned with the customer's actual production requirements, increasing material availability and reducing the risk of interruptions.